The trick: Announced Not Shipped
Nscale promised Britain's largest AI supercomputer in Essex, 23,040 chips by early 2027.
The grid says full power comes in the 2030s, and its only publicly announced customer, Microsoft, has walked.

Loughton will be the UK's largest AI supercomputer, with 23,040 GB300 GPUs delivered in Q1 of 2027.
Before you read on. Your call?
BS
23,040
Free with your account
Sign in for this free check.
This edition’s selected free story opens after sign-in.
There’s more to this story.
Membership opens the full investigation, the strongest counterargument and what to do with what you’ve learned.
30 days free, then A$89 a year. Payment card required. Cancel before the trial ends to avoid the first charge.
Review my 30-day free trial →- At sign-up: 30 days free. Payment card required. One introductory trial per customer.
- Your trial ends 30 days after you start. Unless you cancel before then in Account → Manage subscription, we charge A$89 for the first year. It renews automatically at A$89/yr until cancelled.
- You can ask for a full refund within 14 days after any annual payment, renewals included, with no reason needed, by emailing hello@bskiller.com. This voluntary refund does not limit your rights under the Australian Consumer Law.
By starting your trial, you agree to the Terms.
BS Killer is published by Inferno Tech Pty Ltd, ABN 27 647 413 474.
Get tomorrow’s check free by email.
Couldn't check your access. That's on us.
The trick has a name
We call it Announced Not Shipped: claimed, never released. You'll see it again. Learn to spot it →
Receipts
- Supports nscale.com:
which will be the UK’s largest AI supercomputer when it goes live
- Supports nscale.com:
will initially house 23,040 NVIDIA GB300 GPUs delivered in Q1 of 2027
- Refutes theguardian.com:
Microsoft, one of its largest planned customers and expected to have been the anchor tenant, informed the company that it was pulling the plug on its agreement
- Refutes theguardian.com:
means Nscale has lost its only publicly announced customer for the Essex datacentre
- Refutes theguardian.com:
would not be able to supply enough power to the company’s Loughton datacentre until the early to mid-2030s
- Context theguardian.com:
We remain committed to both the Loughton project and the UK, and we are exploring alternative power sources for the site, in addition to other expansion sites in the UK.
- Context theguardian.com:
The scaffolding yard site has been cleared by Nscale
- Context theguardian.com:
It is understood that Microsoft remains on board for another project the company has in Norway.
- Context theguardian.com:
describing it as the “largest UK sovereign AI datacentre”
- Context theguardian.com:
Doubts had already emerged about the scheme after the Guardian revealed in March that the location was still an operational scaffolding yard
- Context theguardian.com:
could undermine its ambition to float on Wall Street this year
- Refutes runtimewire.com:
may not get enough grid power to operate until the early to mid-2030s, years after its expected 2027 debut
Open the Receipts Pack → What each source proves, every figure traced, and what would change our verdict.