all data center developers made clear that their commitments to paying their "full energy costs" and "full cost of service" refer to the costs of infrastructure exclusively benefitting them
[T]he companies commit to paying for infrastructure that solely benefits them, but dispute how much they should pay for shared infrastructure that is paid for by all ratepayers but was only built to accommodate the data center
The senators questioned Amazon, Google, Meta, Microsoft and others about their energy cost-sharing policies, use of nondisclosure agreements and tax incentives.
When our datacenter expansion requires improvements in transmission and substation capabilities, we will continue our existing practices by paying for these improvements.
First membership: 30 days free, then A$89 a year. One introductory trial per customer. Card required; renews annually until cancelled. Cancel before the trial ends to avoid the first charge.
Free · one story a night
Don't take the AI industry's word for it.
“Cancer, Alzheimer's, heart disease and mental illness will be relics of the past in less than a decade.”
BSHeadline Over FilingDario Amodei, Anthropic CEO, in the company's IPO roadshow video
That's the latest lead check. One a day, receipts attached, in your inbox before someone repeats it at you. Free.
No spam. Unsubscribe in one click. Receipts or it didn't happen.
Pranjal Gupta writes every check himself. Former enterprise architect, from the implementation side. Not a team of anonymous raters.